TILOS for Water & Sewerage Projects

/tilos/tilos-for-water-and-sewerage/

Trunk main and sewer renewal schemes are linear in exactly the same sense a railway is: a pipe route with a start and an end, chambers and manholes at fixed intervals, and site constraints — traffic management, road crossings, environmental permits — that apply to specific stretches, not the whole scheme.

Time-location chart for a 6km trunk sewer renewal showing excavation and pipe-laying activities, manhole markers, and a restricted-hours road crossing
A 6 km trunk sewer renewal — excavation and pipe-laying, manholes marked, and a restricted-hours road crossing slowing progress mid-route.

Why water and sewerage schemes need time-location scheduling

A utilities scheme’s biggest scheduling risk is usually a fixed point along the route — a live road crossing, a watercourse, a section next to a school — where working hours or methods are restricted. A Gantt chart treats the whole activity as one bar with one rate; a time-location chart shows the rate actually change as the crew passes through that constrained stretch, which is exactly the behaviour a realistic schedule needs to capture.

What the chart above shows

Excavation & shoring, followed by pipe laying, progress down a 6 km trunk sewer. Manhole chambers are marked at regular intervals along the chainage axis — useful reference points for site teams reading the chart. A shaded band marks a restricted-hours road crossing: both activity lines visibly flatten as they pass through it, showing the real production-rate impact rather than hiding it inside an averaged duration.

Typical constraints TILOS helps you plan around

  • Restricted working hours at live road or rail crossings
  • Environmental permit windows near watercourses or protected sites
  • Access sequencing where excavation, pipe laying and reinstatement can’t all occupy the same short stretch at once
  • Coordinating with other utilities sharing the same corridor

Who uses this

  • Planners scheduling excavation, pipe-laying and reinstatement crews
  • Project managers tracking overall completion against permit deadlines
  • Risk managers monitoring exposure at fixed constraint points along the route