TILOS for Oil & Gas Pipelines

/tilos/tilos-for-oil-and-gas-pipelines/

Cross-country pipeline construction is planned in “spreads” — stringing, welding, trenching & lower-in, backfill & reinstatement — each following the one ahead of it down the full length of the route. Over 100+ kilometres, environmental and seasonal constraints at specific crossings make this one of the clearest cases for time-location scheduling in any sector.

Time-location chart for a 120km cross-country pipeline showing four construction spreads and a shaded environmental river-crossing work window
A 120 km cross-country pipeline — four spreads, and a shaded environmental work window at a river crossing.

Why pipeline programmes need time-location scheduling

A river or wetland crossing on a pipeline route often carries a hard environmental work window — construction permitted only outside a fish-spawning or bird-nesting season, for example. That constraint applies to a specific chainage, not a specific week of the whole project. A time-location chart shows exactly which spread’s line passes through that chainage, and when — turning a permit condition buried in an environmental management plan into something visible on the schedule itself.

What the chart above shows

Four spreads — stringing, welding, trenching & lower-in, and backfill & reinstatement — progress down a 120 km route at their own realistic rates, each starting once the spread ahead has cleared enough chainage. A shaded band marks an environmental work window at a river crossing around chainage 58–64 km: any spread’s line entering that band outside the permitted period is an instant, visible planning problem rather than something discovered on site.

Typical constraints TILOS helps you plan around

  • Environmental and seasonal work windows at watercourse or protected-habitat crossings
  • Right-of-way and land access agreements that apply to specific chainage sections
  • Multiple contractor spreads working the same route at different rates
  • Tie-ins and interfaces with existing pipeline infrastructure at fixed chainage points

Who uses this

  • Planners coordinating multiple spreads along the same route
  • Project managers reporting progress against permit and consent deadlines
  • Contracts managers evidencing environmental-window-related delay
  • Risk managers tracking exposure at fixed environmental or land-access constraints